Whatever it is, the way you tell your story online can make all the difference.

Project I

Just finished another kitchen and bathroom in Bedminster

Client
Name here

Year
09/27/2023

Project II

Client
Name here

Year
09/04/2023

Just finished another kitchen and bathroom in Bedminster

Project III

Client
Name here

Year
09/04/2023

-I moved the fridge into the pantry on the other side of the kitchen by enlarging the pantry and installing waterline and electricity.

-Then I built a half-wall between the kitchen and living room and built an island next to itl with additional storage underneath and to the side. I could have added a center island but that would limit the space to move around in the kitchen

-The counter is in quartz and the backsplash is in marble. I installed new flooring.

-We finally reconfigured the placements of the stove etc to allow optimal utilization and ventilation.

This is a completely remodelled kitchen in the Meadows community in Hillsborough. The original kitchen had very limited counter space. We completely reconfigured the space. This was a bigger project that took 15 days.

Project IV

Client
Name here

Year
09/04/2023

This was another kitchen I built in the Ridge townhouse community. The cabinets are solid wood in Shaker style in the Stone-colored stain. The counter and backsplash are both Quartz in Calacatta. The work finished in 4 days.

Day -45: Ordering cabinets (this color was not in stock so it took 6 weeks to arrive. In stock colors arrive in 10 days)

Day 0: Client cleans belongings out of kitchen. I assemble the RTA cabinets in my workshop

Day 1: Demolition

Day 2: Installing base cabinets. Taking measure for stone counter.

Day 3: Installing stone counter. Installing top cabinets. Done!